Progress report as on 15th FEBRUARY 2008.
To see the progress photographs, click here.
 
  1. Water proofing for toilets for all the buildings almost Completed.
  2. STP electrical work is also completed.
  3. ION Exchange filtration plant for water purification is installed.
  4. Road work and compound wall work is in progress.
  5. Basement gutter work is completed.
  6. Basement concreting work is over.
  7. Lift work is nearing completion.
  8. External plastering is completed.
  9. Stair case tiling is completed.
  10. Corridor tiling is completed.
  11. Fire fighting system is nearing completion.
  12. Painting work is in progress.
  13. External Drainage work is in progress.
  14. Granite work is nearing completion.
  15. Aluminum work is in progress.
  16. Generator installation work is in progress.
  17. Roof water proofing work is completed.
  18. Electrical panels are in place.
   