Progress report as on 15th FEBRUARY 2008.
To see the progress photographs, click here.
- Water proofing for toilets for all the buildings almost Completed.
- STP electrical work is also completed.
- ION Exchange filtration plant for water purification is installed.
- Road work and compound wall work is in progress.
- Basement gutter work is completed.
- Basement concreting work is over.
- Lift work is nearing completion.
- External plastering is completed.
- Stair case tiling is completed.
- Corridor tiling is completed.
- Fire fighting system is nearing completion.
- Painting work is in progress.
- External Drainage work is in progress.
- Granite work is nearing completion.
- Aluminum work is in progress.
- Generator installation work is in progress.
- Roof water proofing work is completed.
- Electrical panels are in place.
|
|
|
|
|
|
|